RFP for saglemi issued

-Inviting private companies to complete houses
By Selorm GBORBIDZI, Accra
Government has issued a Request for Proposal (RFP), inviting private sector participation in a move to finally address the long-stalled Saglemi Housing Project.
The Request for Proposals commenced yesterday, April 17, and is set to end on July 8.
This initiative marks a significant shift in strategy, aiming to leverage private expertise and resources to complete the project and contribute to bridging Ghana’s housing deficit.
The housing project, initiated in 2012, has been plagued by controversy and delays.

Originally envisioned to deliver 5,000 affordable housing units, the project was scaled down to 1,506 units before being abandoned due to legal issues.
The partially built structures have suffered from vandalism and theft, adding to the overall project woes.
Announcing government’s plans to engage the private sector towards the redevelopment of the housing units at a brief ceremony in Accra yesterday, Minister for Works and Housing, Kojo Oppong emphasized government’s commitment to seeing to it that the units are redeveloped and handed over for usage. “Ghanaians want the phenomenon of uncompleted or abandoned mass housing projects to come to an end.
“Till date some of the projects from the President Kufour era are still uncompleted. It adds to the narrative that we don’t finish projects when we start.
“We have a housing deficit of 1.8 million that we’re trying to reduce as the years go by.
“Already, there are about 40,000 housing units a year that we deliver as a country.
“That is not enough to close the gap so if all of these projects keep hanging out there, it will deter future projects from being embarked upon.
“That is why it’s very important that we take advantage of this opportunity to reverse this trend,” he explained.
He said the newly issued RFP seeks experienced and reputable local and international investors to partner with the government in a partnership that aims to not only address the housing shortage but also contribute to Ghana’s socio-economic development.
Speaking on the specifics of the RFP, Chris Pobee Abbey, Director of Housing and a member of the Technical Working Committee overseeing the project, outlined the key objectives for potential partners.
These he said includes completing all 1,506 housing units; developing essential infrastructure like electricity, water supply, proper sanitation, and road networks; ensuring adherence to all legal and regulatory requirements and securing complete financial backing for the project’s successful completion.
The evaluation of proposals will be based on a 70/30 split, with 70% weightage given to the financial strength of the bid, including the robustness of the financial plan, evidence of sufficient resources, and a plan for operational sustainability.
The remaining 30% will focus on the technical aspects of the proposal, including alignment with project objectives, experience of the bidder, proposed innovative solutions, potential community impact, and a strong risk management plan.
On her part, Dr. Theresa Tuffour, a director at the Ministry who also serves on the Technical Working Committee, assured the public that the selection process for a strategic investor will be conducted with the utmost transparency, integrity, and accountability.
“The entire selection process will be conducted with fairness, integrity, and accountability,” she assured. “We want Ghanaians to be confident that this project is being completed for their benefit.”
Presenting the RFP’s timeline, an Architect with the Ministry, Foster Oseae Akunnor announced that prospective bidders have until July 8th, 2024, to submit their proposals.
Contract signing with the chosen partner is slated for August 30th, 2024.
He said the Ministry looks forward to receiving strong proposals and partnering with a qualified firm to complete the project.
$114m additional investment needed
Consequently, $114 million in additional investment from the government is needed to complete all outstanding works to make the 1,506 Housing Units habitable.
$68m needed to complete housing units
An assessment of the project based on reports from Architectural and Engineering Services Limited (AESL) and the Ghana Institution of Surveyors (GhIS) revealed that $68 million is required for the completion of 1,506 housing units and other on-site infrastructure works of the project.
$30m required for water supply
The Community Water and Sanitation Agency estimates that $30 million is needed to connect water to Saglemi.
$8m needed for Electricity supply
Also, the Electricity Company of Ghana (ECG) estimated that $8 million will be required to extend service to the area to serve the facility.
$5m to provide storm drains
Estimates from the Ghana Hydrological Authority (GHA) quoted $5 million as the amount needed to provide storm drains.
The original output target of the Saglemi project of 5,000 units is $200 million as stipulated in the financing agreement.’
Currently, an amount of approximately $196.4 million ($196,428,891.66), representing 98%, has been expended on 1,506 units as against the planned 5,000 units.
Executive approval
In August 2012, the then-President John Dramani Mahama granted executive approval to the Ministry of Water Resources, Works and Housing for the construction of 5,000 affordable housing units (the Saglemi Affordable Housing Project) for sale to workers through mortgage arrangements provided by Ghana Home Loans to be implemented by Construtora OAS Limited.
Credit Suisse offered Buyer’s Credit of $200m
The project was to be funded by a Buyer’s Credit of $200 million provided by Messrs Credit Suisse International (Credit Suisse).
Parliament granted approval on October 31, 2012
On October 31, 2012, Parliament granted approval for the government to secure a facility of $200 million from Credit Suisse for the construction of 5,000 affordable housing units by Messrs Construtora OAS Ghana Limited, following a joint memorandum to Parliament by the then Minister Enoch Teye Mensah, and the then Minister for Finance and Economic Planning, Dr Kwabena Duffour.
Facility Agreement signed on January 4, 2013
On January 4, 2013, a Facility Agreement was signed between the Ministry of Finance, as the borrower, and Credit Suisse, as the creditor, for a facility of $200 million for the construction of 5,000 housing units.
EPC agreement signed on January 4, 2013
On the same day, the then-minister, E.T. Mensah, signed an Engineering, Procurement, and Construction (EPC) Agreement with Construtora OAS Ghana Ltd for the construction of affordable housing units at Saglemi in the Greater Accra Region.
2,172 Acres of land
The project, which was to be executed in four phases on 2,172 acres of land, was at a contract price of $200 million, including consultancy services.
Escrow Management Agreement
An Escrow Management Agreement, a condition precedent to the release of the facility to the borrower, was also signed pursuant to the Facility Agreement and the EPC Agreement between the Ministry of Finance (Borrower), Works and Housing Ministry (Account holder), the Bank of Ghana (Account holding bank), and Construtora OAS (Contractor).
Proper application of funds
The purpose of this agreement was to ensure that the $200 million facility would be properly applied towards the development of the 5,000 housing units.
Payment procedure
The agreement, therefore, required payments under the contract to be effected only when specific works had been duly executed, verified, and certified by the consultants of the project, Architectural and Engineering Services Ltd. (AESL).
EPC Agreement provided for an advance payment of 40%
The EPC Agreement provided for an advance payment of 40% of the contract price to the contractor within five working days of the receipt of the facility in the Escrow Account.
The advance payment was to be applied towards specific works set out in the contract.
Specific project milestones
The remaining amount of the contract price was to be paid to the contractor based on the fulfillment of specific project milestones.
The contractor was required under the agreement to set out the details of the achieved project milestones, which had to be verified and certified by the consultants before receiving payment.
Credit Suisse disbursed $200m on January 9, 2013
On January 9, 2013, Credit Suisse disbursed an amount of $198,450,000, representing the $200 million Jess fees and transaction expenses into the Escrow Account.
12.5% interest rate per annum
Per the agreement, the $200m has a grace period of two years and repayment period of five years at a 12.5% interest rate per annum on the cedi equivalent of the dollar loan amount based on dollar cedi exchange rate fixed at drawdown.
$249.6m was estimated total debt to be serviced
The total debt to be serviced was estimated to be $249.6 million while total sale proceeds of the 5,000 housing units will bring in $257.27 million.
2-bedroom for $29,000, 3-bedroom for $57,000
According to the agreement, the 2-bedroom unit is to be sold at $29,000 while the 3-bedroom unit is to be sold at $57,000.
$80m paid contractor on February 27, 2013
On February 27, 2013, an amount of $80 million, representing 40% of the contract sum, was transferred to Construtora OAS as an advance payment.
$196.4m spent on the project
A total amount of $196.4 million ($196,428,891.66) has been spent on the project.
$179.9m paid to contractor
But, according to the documents filed in court, the contractor who executed the Saglemi project was paid $179.9 million ($179,904,757.78) despite executing work worth $64 million ($64,982,900.77).
Construtora wrote to terminate the contract
On February 18, 2019, the contractor, Construtora OAS Ghana Limited, wrote to terminate the contract with the government.
Contractor demands compensation
The contractor has, in another letter dated March 8 and signed by directors of the company, Charles Maia